Fighting nitrate pollution in Canterbury: MHV

ELI v Canterbury Regional Council & MHV Water Limited

We challenged Environment Canterbury over their decision to grant a nitrogen discharge consent to MHV Water Ltd. While the High Court found the consent unlawful, the judge declined to quash it. In September 2025, we lodged an appeal.

The MHV irrigation scheme covers an area of 138,000 ha between the Hakatere and Rangitata rivers in Canterbury. In 2021, Environment Canterbury issued a discharge consent to the MHV scheme, which allows scheme farms across the area to pollute water with wasted nitrogen (as nitrate) from their farming activities.

Environment Canterbury should be guaranteeing communities have access to clean drinking water and protecting precious freshwater ecosystems. Yet many of Canterbury’s aquifers and lowland waterways are already degraded. In 2020, Environment Canterbury estimated that 62% of private wells in the MHV area may have concentrations of nitrate greater than the maximum allowable value.

Our case

We filed for a judicial review of the Council’s consent decision in August 2024 and in May 2025, we made our case in the Christchurch High Court.

We argued that the Council failed to properly take into account the potential effects of the nitrate discharges on local drinking water supplies.

Our arguments also built on our successful challenge to Environment Canterbury’s decision to grant a consent to Ashburton Lyndhurst Irrigation Limited (ALIL), which neighbours the MHV irrigation area.

Our challenge to Environment Canterbury’s consent for the MHV scheme focused on two key grounds:

  1. The Council failed to take steps to revoke MHV’s consent when it became clear that it had been granted according to the same approach found to be unlawful in the ALIL case.

  2. The Council issued the consent without notifying local community drinking water operators or owners of private drinking water wells in the area.

  • In 2022, we filed a judicial review of Environment Canterbury’s decision for the ALIL consent. The High Court ruled in March 2024 that the Council’s decision to grant the discharge consent was based on a material error of law. The consent issued to ALIL was set aside.

    The material error of law
    In making the decisions for both the ALIL and MHV consents, the Council-appointed Commissioner found that the nitrogen discharges from past and current farming practices had caused significant adverse effects on aquatic life.

    The Commissioner granted the consent in both cases, even while acknowledging that section 107(1) of the Resource Management Act 1991 (RMA) prohibits councils from granting discharge consents if the discharge is likely to give rise to “any significant adverse effects on aquatic life”. The Commissioner granted the consent based on ALIL and MHV’s respective reductions in nitrogen discharge allowances pledges for continuous improvement.

  • After our High Court win regarding the ALIL scheme in March 2024, the farming industry successfully lobbied the government for a law change. In October 2024 the government passed an amendment to section 107 of the RMA under urgency, and without public consultation.

    The amendment allows consent authorities, such as Environment Canterbury, to grant discharge permits for activities that could cause significant adverse effects on aquatic life, if the receiving waters were already subject to significant adverse effects and the permit conditions would contribute to a reduction in those effects over time.

    The effect of this law change is that councils will be able to consent more pollution such as nitrate into rivers, lakes, wetlands and estuaries, which would have otherwise been prohibited.

    Even so, scheme consents still need conditions which satisfy the Council that the pre-requisites of the amended section 107 of the RMA will be met; that they will contribute to a reduction in significant adverse effects on aquatic life over the duration of the consent. This has yet to be tested by the courts.

High Court judgment

In early September 2025 we received the MHV judgment from the High Court:

  • The Court found in ELI’s favour that Environment Canterbury had made a material error of law in granting the consent to MHV Water Ltd, breaching section 107 of the Resource Management Act.

  • However, because the Government weakened freshwater protections in section 107 in favour of polluters, the Court declined to overturn the consent. The Court’s position was that, should the consent be revoked and reconsidered under the new legislative regime, it would end up being granted because of the law change.

  • The Court also found that Environment Canterbury had failed to apply relevant coastal policy provisions. However, this failure was not considered material to the granting of the consent.

  • Our challenge to Environment Canterbury’s non-notification decision on the basis of the effects of nitrate pollution on drinking water were not upheld.

Our appeal

In late September, we filed an appeal of the High Court's decision, with the Court of Appeal.

We believe the Court erred in its judgment, that should the consent to MHV be reconsidered under the amended s 107 of the RMA, the consent would still be granted. Our view is that the effects from the nitrate discharge associated with the scheme are not inevitably lawful.

ELI considers that the Court was wrong to uphold the Council’s decision not to notify the public of the consent application. ECan’s own estimates showed that hundreds of private drinking water supplies in the MHV command area were at risk of exceeding the allowable value of nitrate.

ELI also takes the view that the Court was wrong when it found that the Council’s failure to consider relevant coastal plans and policies was not a material error of law sufficient to invalidate the decision.

Finally, ELI says the Court erred in finding that section 46 of the Legislation Act 2019 does not empower a consent authority to revoke an unlawfully granted resource consent. ELI says that this interpretation means that when systemic legal errors in consent approvals are found, councils are not empowered to fix them.

We are now awaiting a hearing date for our appeal.  

 

Case timeline

August 2024 - Filed for judicial review

October 2024 - The Government amended section 107 of the RMA

May 2025 - Hearing held in the Christchurch High Court

September 2025 - Judgment released

September 2025 - Appeal filed with Court of Appeal

 
 

Related cases

 
Appeal filed
Previous
Previous

Crayfish case #2: restoring crayfish numbers in Northland

Next
Next

Crayfish case #1: Restoring crayfish numbers in Northland